| Paul Chandler |
 |
Recent experience of working with two UK law firms, Norton Rose and Osborne Clarke, helping them reduce the cost of their support goods and services.
Versatile Consultant, Project and Interim Manager, with an exceptional track record for delivering very significant financial and operational returns.
Accomplished negotiator, hands-on as well as strategic thinker. Diverse procurement category experience and cost control achievement in Banking, Commercial Law Firms, Capital Projects and Facilities, Healthcare Technology, Oilfield and Rail. |
 |
 |
|
 |
| Qualifications |
 |
CIPS Diploma Postgraduate Diploma in Management Studies with award for outstanding performance Roffey Park Strategic Leadership Programme HNC Business Studies (Distinction) |
 |
| Professional Associations |
 |
| Full Member of both CIPS and of CMI. |
 |
| Key skills and achievements |
 |
Norton Rose Analysed £30m spend identifying, project planning and executing key cost reductions achieving 10% savings. Particular focus on IT and professional services. Developed policies, procedures and processes. Recruited successor and devised business plan |
 |
Osborne Clarke Analysed £6.5m spend, identified savings opportunities, planned and executed project to achieve 10% savings. Particular focus on IT and professional services. Coached management team in best practice procurement. |
 |
Barclays Identified and led negotiations for 5% savings from a £550m outsourced mortgage processing contract. Analysed E2E supply chain of a further £200m spend and identified additional savings. |
 |
Abbey National Set up and managed two buying groups £325m spend, achieving 15% savings. Established user relationships and credibility. Revamped operations, developed policies and best practice procedures. |
 |
EC Harris Analysed £35m spend for cost reduction and service level improvement opportunities, risk, processes, human resources and development needs. Achieved 5% savings. Set up procurement function gaining stakeholder buy-in. |
 |
Amersham Developed and implemented least cost, best practice Y2k compliance project, managing a global programme. Project managed a corporate purchasing card implementation. |
 |
BP Six multi £bn procurement projects. Advanced project management techniques within accelerating programmes. Very major cost reduction initiatives for project viability in an era of low oil prices. |
 |
Railtrack Developed a procurement business plan for 10% savings on £2.4bn spend and procurement policies & procedures. Executed pre-privatisation audit and consequent performance improvements. |
 |